Aircraft maintenance checks using critical chain project path

The paper compares the traditional project management method with critical chain project management (CCPM) in view of reducing the aircraft down time duration for maintenance. This paper repositions buffers and other techniques to shorten the chain path and a reduction in the total duration of the project by five days is achieved.